Chapman Elementary School – Anchor Point, AK

The Chapman Elementary School project consisted removal of hazardous materials and replacement of exterior windows and siding. This also included other misc finishes on the exterior and interior to complement the main points of the contract. Blazy was able to work in the confines of the time frame to get the long lead siding ordered and installed prior to school starting for the following year.

 

 

Blazy’s Role: General Contractor

Construction Cost: $250,000

Construction Period: June ’17 – Aug ‘17

Delivery Method: Design-Bid-Build

Owner: Kenai Peninsula orough

A/E Firms: K+A Designstudios