Seward Visitor Center – Seward, AK

The Seward Visitor Center included a complete exterior and interior remodel with the addition of an elevator. This also included added electrical systems to help facilitate audio and visual equipment involved in a separate contract for displays within the building. Some of the more difficulties of the project including adding the addition during the rainy part of the year in Seward prior to wintertime. The new finishes included new siding, roofing, flooring, ceilings and a unique finished painting scheme.

 

 

Blazy’s Role: General Contractor

Construction Cost: 1,700,000

Construction Period: Sept ’17 – May ‘18

Delivery Method: Design-Bid-Build

Owner: National Park Service

A/E Firms: RIM Architects, Reid Middleton, RSA Engineering